[Progress.044] Scaffolding up, ready for 1st floor frames!

This morning we have 2 trades person working on the frames. There's this truck with generator running, supplying power to the workers. As we have warned our builder about our super fussy neighbours many many times, they won't be stealing electricity or water, as reported by epiphany in this homeone.com.au post: "Problems with people building next door".

They are busy hiding, sorry I mean working behind the frames...

When I revisited our site again around 9 pm, I was quite surprised to see lots of scaffolding been installed. They even moved all the frames stacked at the front this morning up above the other frames. Well done! Looks like we are ready for the crane!

This is from the garage side...

Quickly checked the weather forecast again:

Forecast for Tuesday
Early shower, then fine. Light to moderate westerly winds, becoming fresh and gusty in the afternoon and evening.
Precis: Early shower, then fine.

Not 100% perfect day for crane, but after that it's "Fine" until next Monday... Getting really exciting now... Wonder what it looks like to have a huge crane struggling through the "jungle" of wires... I wish they could "accidentally" knock down my neighbour's wire, so that I can get rid of the ugly tiger tails...

Friday, 7 September 2007

[Progress.043] More beams setup, more frames delivered

When I checked our site this afternoon, I saw most of the timber beams been setup.

This one is from the other side, viewing from the garage's direction.

There were also some more frames delivered, probably for the 1st floor.

Remember last time I mentioned they setup this big steel beam on top of 2 tiny timber frames? They now placed even more timber beams on top of the steel beam, making it even more heavier for the 2 tiny frames below. Great, looking even more dangerous to me!

And I also noticed there were a lot more rubbish all over the places. Have a closer look, I found that some of them are actually sketches/drawings for other construction sites! This one is about how the beams should be placed for a house in Roseville.

This one is about a house building with Wincrest homes.

This one is about a house in Oatley for Mr/Mrs Little building with Trident Homes. I am not happy about this. If these guys can dump other houses' drawings on my site, that means they could also be dumping mine somewhere else...

I checked the wires at the front. As shown below, may be they are right. The wires are indeed a bit messy...

According to our builder, if weather permits, the crane will be here around next Wednesday. Quickly checked the weather forecast: rain should stop after Sunday and stay sunny for a few days, sweet!

Thursday, 6 September 2007

[Progress.042] Need a crane for 1st floor frames?

I thought there won't be any progress in the past few days due to continuous rain. But according to our builder, the carpenter was on-site yesterday and should have some progress with the frames. Will check our site again during the "thanks to APEC" long weekend.

They also mentioned as there were quite a lot of electrical wires at the front of our site, they will need to hire a crane to drop the frames for 1st floor on top of the existing ones. Well, since they have inspected the site so many times, if cranes are required then just do it!

Saturday, 1 September 2007

[Progress.041] Some beams setup, more gravels, damaged frame replaced

We have 2 trades person on-site yesterday, and they told me they will be working on the frames. I thought they will setup the frames for 1st floor, when I checked it this morning, the frames seems remaining the same. As shown below, there are actually some changes - some of the orange beams are been installed.

Also, the other day the gravels were only up to the gates. Now it's all the way up to the slabs.

Another achievement is we can now clearly see the damaged frame has been replaced. But why do they leave the damaged timber at the front is beyond me, is that to prove that they have done the work??

The other thing I don't quite understand is, why would they leave this big steel beam above the garage doors on top of 2 small timber. Looks quite dangerous to me... Or are they trying to show everyone how strong the frame timbers are??

I have a closer look yesterday morning, the big window been left at the front the other day was actually the sliding door.

Saturday, 25 August 2007

[Progress.038] More tiger tails, and a few other stuffs

The rain has been on and off for the past few days, so there wasn't much progress today, except the tiger tails.
As requested by the site supervisor, we added some more tiger tails today, another unplanned expense... There used to be 6 (3 pairs) of them, now we have extra 8, total of 14 installed as 7 pairs...

The entrance was very muddy, we discussed with site supervisor and he agreed to order some gravels very soon. There's another site building with Masterton near our area, they have lots of gravels in the entrance and it looks much better than ours.

I think these boards are the flooring boards for 1st floor. With the yellow tongue thing they can be joined together easily.

This is a closer look of the beams to support the flooring boards.

This is the right hand site of the house, can vaguely see the windows spaces at the back. They might look the same to you but we are already matching it against our drawings and start seeing the shapes of each area been created like a big LEGO puzzle. And yes, how can I forget the damaged frame for the front bay window...

This one is the other side, for the areas behind garage.

A closer look of the seweage pipe, looks ok to me, but wife quite concern about the status about the pipe below. Hopefully after the gravels added it will be much better.

A closer look of the steel beams. There are about 8 of them, don't know why we need so many of them.

I think the 8 (4 pairs) of them shown here with 2 big screws are the stand for supporting the beams. But if there are 8 steel beams, and 4 pairs of stands, how are the other 4 going to be supported?? By timber frames?

Saw this bottle on the ground, labelled as "Iplex Pink Priming Fluid". Found this web page talking about "Iplex priming fluid must always be used when making solvent weld joints. It is generally coloured pink for identification although clear is also available." I read it a few times but still don't quite understand what is it talking about...

Friday, 24 August 2007

[Progress.037] Frames for ground floor done

Got some photos from yesterday here.
When I walked past our site yesterday morning, a truck just unloaded some bright orange coloured steel beams. There were 2 trades person on site working on the frames.

When I visited it again last night, I found the pipe that was suppose to allow rain waters to flow out to the road was blocked by mud. Have to ask our builder to clean it up.

Good to see they finally moved all the timbers inside.

Have a closer look at the beams, looks quite strong... What surprised me is the steel mesh... Not the grey one, the grey one is the fence, it's the yellow one I am talking about. They are the left overs from the slab, and it's all rusted...Are we sure this thing is strong enough to be used as part of our slabs??

This is part of the bay window at the front for our ground floor. Did you notice something unusual?

Yes, the damaged frame I mentioned in previous post. Isn't it very obvious? Even a 5 years old can see that it's damaged, then why is it still been used??!! Will talk to our builder to get it fixed...

The other side of ground floor. It's very dark and the other areas are not very clear. Will try to get better photos during day time next time...

I think the frames for ground floor is done. It looks more like a house now, can't wait to see they finish all the frames...

Wednesday, 22 August 2007

[Progress.036] One of the frames damaged

This post should actually be placed before [Progress.035]...

I took some much clearer photos this morning.


If you look closely at the last photo in the post [Progress.034], you might notice a damaged frame. This is a closer look of the damage, will raise that as an issue to the builder.

Tuesday, 21 August 2007

[Progress.034] Frames Delivered

My family told me some timber stuffs were delivered, so I took my camera with me during my jogging. As shown below, the frames are here!

It's quite dark and the photos weren't quite clear, might try to get better ones tomorrow morning.

I think there should be more to come as what I saw doesn't seem to be enough for a 2 storey house. Will have a clearer view tomorrow morning.

Unfortunately it started to rain, wonder when will they start setting up all the frames...

Monday, 9 July 2007

[Jargon.001] Timber frames and ceiling

If you are like me, who doesn't know much about all the technical terms/jargons used in the construction industry, it can be quite painful understanding what the trades person said or explaining to someone what you tried to do. So I think it would be helpful to start collecting some diagrams/drawings that clearly show what some of the terms actually mean.

Let's start with the followings:
These 2 are from Boral:


This is from greenhouse.gov.au click here for the original page