Achievements:
1. 1st floor eaves lining done.
2. 1st floor sarking done.
3. Roof tiles delivered.
Unplanned expenses:
Confirmed $823 for sewer variation.
Issues:
1. Steel beams in Alfresco been joined instead of one full piece, painted with orange paint. Not sure if this is structurely sound and safe
2. Found a hole on the floor board of bedroom above garage
3. 2 "Noggings" in frames of bedroom above garage damaged
4. Sewage pipe (in front of property) broken
5. 1st floor main bathroom windows was installed with clear glass windows instead of obscured/glazed ones
6. Drain pipe next to alfresco post been removed
7. Huge gap above external door and window, especially laundry area