Saturday, 5 January 2008

[WeeklySummary.019] Week 19 (06/12/2007) - (12/12/2007)

Achievements:
1. Air conditioning pipes connected
2. First inspection by our own inspector
3. Cabling for network, alarm system, telephone, home theatre completed
4. Electrical cabling completed

Unplanned expenses:
None

Issues:
1. Steel beams in Alfresco been joined instead of one full piece, painted with orange paint. Not sure if this is structurely sound and safe - According to inspector, an engineering report is required, leave it open for tracking purpose
2. Found a hole on the floor board of bedroom above garage
3. 2 "Noggings" in frames of bedroom above garage damaged - issue resolved
4. Sewage pipe (in front of property) broken
5. 1st floor main bathroom windows was installed with clear glass windows instead of obscured/glazed ones
6. Drain pipe next to alfresco post been removed
7. Huge gap above external door and window, especially laundry area - According to inspector, this will later be covered. Leave it open to keep track of issue
8. Front hip roof above front windows not finished - issue resolved
9. Study room window broken
10. Door frame for sliding door damaged
11. Big hole in roof tile above garage area
12. Standard "J" track (instead of heavy duty "U" track) been used for both sliding doors
13. Front roof valley above bay windows fitted with incorrect length (too short) causes leaking in front porch and bay windows areas
14. Front roof valley above garage leads water straight into sarking area instead of roof tiles
15. Front roof tiles above bay windows not finished properly - picked up by inspector
16. 3 areas in bedrooms upstair have floor movements, squeaking noise is evident in those areas - picked up by inspector
17. 2 air conditioning pipes not sealed properly - picked up by inspector