Achievements:
1. Insulation finished
2. Cornice and materials for gyprock wall & ceiling delivered
3. Cleaning of external bricks for ground floor (not finished due to issue with neighbour)
4. Work for gyprock walls started
Unplanned expenses:
None
Issues:
1. Steel beams in Alfresco been joined instead of one full piece, painted with orange paint. Not sure if this is structurely sound and safe - According to inspector, an engineering report is required, leave it open for tracking purpose
2. Found a hole on the floor board of bedroom above garage
3. Sewage pipe (in front of property) broken
4. 1st floor main bathroom windows was installed with clear glass windows instead of obscured/glazed ones
5. Drain pipe next to alfresco post been removed
6. Huge gap above external door and window, especially laundry area - According to inspector, this will later be covered. Leave it open to keep track of issue
7. Study room window broken
8. Door frame for sliding door damaged - issue resolved
9. Big hole in roof tile above garage area - issue resolved
10. Standard "J" track (instead of heavy duty "U" track) been used for both sliding doors
11. Front roof valley above bay windows fitted with incorrect length (too short) causes leaking in front porch and bay windows areas
12. Front roof valley above garage leads water straight into sarking area instead of roof tiles
13. Front roof tiles above bay windows not finished properly
14. 3 areas in bedrooms upstair have floor movements, squeaking noise is evident in those areas
15. 2 air conditioning pipes not sealed properly - issue resolved
16. Cleaning of external bricks for ground floor half finished
17. Insulation for alfresco area damaged during brick washing process